Comparative accuracy of floor area, storey enclosure and cubic methods in preparing preliminary estimate in Nigeria

dc.contributor.authorAkinsiku, O. E.
dc.contributor.authorBabatunde, S.O.
dc.contributor.authorOpawole, A.
dc.date.accessioned2020-01-15T11:29:49Z
dc.date.available2020-01-15T11:29:49Z
dc.date.issued2011
dc.descriptionStaff publicationsen_US
dc.description.abstractThe aim of construction cost forecasting is to provide an estimate of a construction contract. Construction clients are interested in knowing their financial commitment before the completion of a detailed design. There are various methods used by estimators to forecast the construction cost of building and civil engineering projects. The accuracy of these techniques is, however, impeded by some external factors that need to be overcome or are provided for in order to get a realistic estimated value. This study examined the three most common techniques used in preparing preliminary estimates in Nigeria, namely, the floor area or superficial method, the cubic method and the storey enclosure method. Total construction costs were extracted from the final accounts of 10 bank projects executed within the last 15 months in Lagos metropolis, Nigeria. From the extracted costs, using a random selection, a project was used as the base on which other techniques were used. The data were analysed using their respective deviation from the final cost and the Pearson correlation coefficient was used to test their degree of relationship with the final cost. The study revealed the cubic method of calculating preliminary estimates as having the highest frequency of accuracy closest to the obtained construction value with respect to the 10 projects sampled, whereas the floor area and storey enclosure methods followed behind. However, using the Pearson product moment correlation coefficient, the floor area or superficial method has the greatest relationship to the construction cost; the cubic method came second, whereas the storey enclosure method has the least relationship with the construction cost.en_US
dc.identifier.citationAkinsiku, O. E., Babatunde, S.O., & Opawole, A. (2011). Comparative accuracy of floor area, storey enclosure and cubic methods in preparing preliminary estimates. Journal of Building Appraisal. 6, 315 – 322.en_US
dc.identifier.urihttps://ir.unilag.edu.ng/handle/123456789/7397
dc.language.isoenen_US
dc.publisherMacmillan Publishers Ltd.en_US
dc.relation.ispartofseriesJournal of Building Appraisal;Vol.6
dc.subjectAccuracyen_US
dc.subjectPreliminary estatesen_US
dc.subjectConstruction costen_US
dc.subjectBuildingen_US
dc.subjectResearch Subject Categories::FORESTRY, AGRICULTURAL SCIENCES and LANDSCAPE PLANNINGen_US
dc.titleComparative accuracy of floor area, storey enclosure and cubic methods in preparing preliminary estimate in Nigeriaen_US
dc.typeArticleen_US
Files
Original bundle
Now showing 1 - 1 of 1
Loading...
Thumbnail Image
Name:
jba20119a.pdf
Size:
152.22 KB
Format:
Adobe Portable Document Format
Description:
License bundle
Now showing 1 - 1 of 1
Loading...
Thumbnail Image
Name:
license.txt
Size:
1.71 KB
Format:
Item-specific license agreed upon to submission
Description: