Causes and effects of rework in building projects in Lagos state, Nigeria

dc.contributor.authorAjayi, O. E.
dc.contributor.authorAkinsiku, O. E.
dc.contributor.authorOyeyipo, O.
dc.date.accessioned2020-01-15T10:54:04Z
dc.date.available2020-01-15T10:54:04Z
dc.date.issued2014-01
dc.descriptionStaff publicationsen_US
dc.description.abstractRework occurs as a result of design, construction changes and also as variation which is addition, omission and modification of design. Rework cost is on the increase as a result of these changes and it has indirectly affected contract sum, period of completion and quality of the project. Hence this study intends to examine the causes and effects of rework in building projects. Descriptive research design was used for this study and the population consists of construction professionals from consulting and contracting organization. Simple random sampling technique method was used. A structured questionnaire was used as the principal instrument for collecting data from construction professionals in the industry. A total of 98 questionnaires were distributed and 52 were returned given an average response rate of 52%. Statistical package for social sciences (SPSS) 17th version was used for analysis via descriptive and inferential statistic. The findings of the study indicates that changes, defect and quality deviation are the most significant sources of rework on construction projects. Poor communication with design exerts the greatest influence on the rework occurrence on construction sites. The paper also showed that there is significant relationship between rework cost and initial contract sum, initial and final contract period, with exception of final contract sum. In conclusion poor communication with design consultant, use of poor quality materials and poor workmanship are the main causes of reworks in building projects, hence this will affect the client and the project performance in terms of time, cost and quality standard. The paper recommends that early identification of the causes and sources of reworks by consultants and contractors on building projects will reduce the effect of reworks cost on the contract sum, completion time and changes during the design and the construction changes either from the part of the client or the consultant.en_US
dc.identifier.citationAjayi, O.M., Akinsiku, O. E., & Oyeyipo, O.O. (2014). Causes and effects of rework in building projects in Lagos state, Nigeria. Proceedings of the International Council for Research and Innovation in Building and Construction, 28-30 January 2014 Lagos, Nigeria, pp. 432-441.en_US
dc.identifier.urihttps://ir.unilag.edu.ng/handle/123456789/7388
dc.language.isoenen_US
dc.publisherINTERNATIONAL COUNCIL FOR RESEARCH AND INNOVATION IN BUILDING AND CONSTRUCTIONen_US
dc.subjectChange, cost and time overrun, performance, project, reworksen_US
dc.subjectChangeen_US
dc.subjectCost and time overrunen_US
dc.subjectPerformanceen_US
dc.subjectReworksen_US
dc.subjectResearch Subject Categories::FORESTRY, AGRICULTURAL SCIENCES and LANDSCAPE PLANNINGen_US
dc.titleCauses and effects of rework in building projects in Lagos state, Nigeriaen_US
dc.typeArticleen_US
Files
Original bundle
Now showing 1 - 1 of 1
Loading...
Thumbnail Image
Name:
Ajayi, Akinsiku and Oyeyipo.pdf
Size:
97.86 KB
Format:
Adobe Portable Document Format
Description:
License bundle
Now showing 1 - 1 of 1
Loading...
Thumbnail Image
Name:
license.txt
Size:
1.71 KB
Format:
Item-specific license agreed upon to submission
Description: